Week 9 - Tile, electrical and plumbing going in.

 Tile going on the roof.

 Stucco wrap on the walls.

 
 Recessed lighing going in.

 Kitchen plumbing going in.

 

Saturday, May 19, 2012

Week 8 - More Detail and Decking for Roof

 Roof deck is on.

 Spiral, Dome and balcony

 Looking back at entry, balcony and dome.

 Dining room, balcony, spiral stairs and entry.

 Barrel ceiling in the entry way.

 
 Game room open to family below.

Back of the house moving along.




Saturday, May 12, 2012

Week 7 - Details being added to framing

 
The dome.

Barrel ceiling down center of media room.

Outdoor living/kitchen area.

Groin vault in vestible leading to master bedroom.
 
 
Overview of back of house.