Week 9 - Tile, electrical and plumbing going in.
Tile going on the roof.
Stucco wrap on the walls.
Recessed lighing going in.
Kitchen plumbing going in.
Saturday, May 19, 2012
Week 8 - More Detail and Decking for Roof
Roof deck is on.
Spiral, Dome and balcony
Looking back at entry, balcony and dome.
Dining room, balcony, spiral stairs and entry.
Barrel ceiling in the entry way.
Game room open to family below.
Back of the house moving along.
Saturday, May 12, 2012
Week 7 - Details being added to framing
The dome.
Barrel ceiling down center of media room.
Outdoor living/kitchen area.
Groin vault in vestible leading to master bedroom.
Overview of back of house.
Saturday, May 5, 2012
Week 6 and Things are starting to take shape!
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
This was an awesome dive!
About Us
We live in Texas and enjoy a variety of activities including being active in our church, enjoying our children and grandchildren and scuba diving.
Blogs
Cameron & Lindsay
Dave & Robin
Tabatha & Clay
Tiffany & Matt
Followers
Blog Archive
►
2013
(12)
►
July
(3)
►
June
(1)
►
May
(2)
►
April
(6)
▼
2012
(28)
►
December
(1)
►
November
(2)
►
October
(4)
►
September
(5)
►
August
(4)
►
July
(4)
►
June
(4)
▼
May
(4)
Week 9 - Tile, electrical and plumbing going in.
Week 8 - More Detail and Decking for Roof
Week 7 - Details being added to framing
Week 6 and Things are starting to take shape!
►
2010
(6)
►
March
(2)
►
February
(1)
►
January
(3)
►
2009
(3)
►
December
(2)
►
April
(1)